Preliminary pipeline route review
Complete survey, environmental, and engineering studies
Landowner Information Session
Commence acquisition of necessary land rights
Submit State & Federal applications for regulatory approvals & permitting, including FERC 7(b) & 7(c) Certificate
Anticipated FERC Approval
Anticipated receipt of all environmental permits and commencement of timber clearing and site activities
Construction begins
Target in-service date