Line N Project Timeline | National Fuel Gas Company

Line N Project Timeline

Line N Project Timeline

How our projects progress:

Spring 2026

Preliminary pipeline route review

March-August 2026

Complete survey, environmental, and engineering studies

September 2026

Landowner Information Session

September 2026

Commence acquisition of necessary land rights

October-November 2026

Submit State & Federal applications for regulatory approvals & permitting, including FERC 7(b) & 7(c) Certificate

October 2027

Anticipated FERC Approval

January 2028

Anticipated receipt of all environmental permits and commencement of timber clearing and site activities

Early Spring 2028

Construction begins

Fall 2028

Target in-service date