Project Timeline (Northern Access Project) | National Fuel Gas Company

Project Timeline

Project Timeline

How our projects progress:

March 2014

Began preliminary route review.

May 2014

Held Supply informational meetings and contacted landowners.

May 2014 — February 2015

Conducted environmental and engineering studies of preferred route.

July 2014

Began FERC NEPA pre-filing process.

August 2014

Held additional public meetings, including Empire.

November 2014

Held FERC Supply scoping meetings.

March 2015

Submitted FERC 7(b)/7(c) filing.

May 2015

Held FERC Empire scoping meeting.

May 2015

Began right-of-way acquisition.

May 2015 – December 2016

Completed additional studies.

February 2017

Received FERC 7(b)/7(c) certificate.

As early as fiscal 2022

Planned in-service date.