Project Timeline (FM100) | National Fuel Gas Company

Project Timeline

Project Timeline

How our projects progress:

October 2018

National Fuel submits RFP for third-party contractor to FERC project manager.

November 2018

National Fuel submits an updated stakeholder mailing list.

November 8, 2018

National Fuel conducts open house for new compressor station location in Clinton County, PA.

December 2018

National Fuel submits updated draft environmental Resource Reports 1 and 10.

April 2019

National Fuel submits remaining drafts of environmental resource reports in a staggered manner.

Summer 2019

National Fuel files Section 7(b) and 7(c) application.

Summer 2020

Commission issues the certificate of public convenience and necessity and authorizes abandonment.

Fall 2020

National Fuel files the implementation plan.

February 2021

National Fuel receives FERC Notice to Proceed.

February/March 2021

National Fuel begins construction.

December 2021

National Fuel places project facilities into service.