Line N System Upgrade Project

Line N System Upgrade Project

National Fuel Gas Supply Corporation (Supply), a subsidiary of National Fuel Gas Company, plans to seek approval from the Federal Energy Regulatory Commission (FERC) to construct various new pipeline facilities in Mercer, Lawrence, Beaver, Washington, and Greene Counties, Pennsylvania to modernize various portions of the Line N system and expand access to locally produced natural gas.

pipeline icon

About the Project

The Line N System Upgrade Project will consist of:

  • Replacement of approximately 6 miles of Line N20 vintage 20-inch pipeline with 24-inch high-strength coated carbon steel, including the Ohio River crossing in Beaver County, PA
    • Includes the installation of two facilities used to inspect and maintain the pipeline, along with safety valves designed to quickly isolate sections of the pipeline if needed
  • Replacement and testing of approximately 1 mile of pipeline segments on Line N20 between Service Creek Road and Aliquippa stations in Beaver County
  • Installation of overpressure protection facilities between Line N20 and Line NM50 near Ellwood City in Beaver County
  • Minor modifications at Supply’s existing Buffalo Compressor Station in Washington County
  • Minor modifications at Supply’s existing Mercer Compressor Station in Mercer County
  • Construction of a new interconnect with a local producer in Greene County
  • Construction of a new measurement and regulation station in Beaver County

Project Map

 

investing money icon

Positive Economic Impacts on Region and Community

  • Investing approximately $100 million in Southwest Pennsylvania
  • Creating approximately 300 jobs during construction
  • Supporting local businesses during construction and operation
two calendar icon

Proposed Timeline

TimeframeProject Status
Spring 2026Preliminary pipeline route review
March-August 2026Complete survey, environmental, and engineering studies
September 2026Landowner Information Session
September 2026Commence acquisition of necessary land rights
October-November 2026Submit State & Federal applications for regulatory approvals & permitting, including FERC 7(b) & 7(c) Certificate
October 2027Anticipated FERC Approval
January 2028Anticipated receipt of all environmental permits and commencement of timber clearing and site activities
Early Spring 2028Construction begins
Fall 2028Target in-service date

pipeline icon

Pipeline Safety

  • Installation of safe and reliable pipe, materials, and equipment and integration into proven safety management system
  • Outstanding safety record
  • Pipeline facilities are constructed and maintained to meet or exceed federal safety code:
    • High strength carbon steel pipe with modern fusion bonded epoxy coating
    • Coating protected with Rockshield and/or select screened backfill
    • Minimum 3 foot of cover
    • 100% of welds are X-rayed
    • Hydrostatic testing
    • Remote control valve installation
  • Proven Construction Quality Management System
  • System monitored 24/7/365 by National Fuel Gas Control
    • Regulated and inspected by the U.S. Department of Transportation (DOT) and Federal Energy Regulatory Commission (FERC)
community icon

About the Company

National Fuel Gas Company, incorporated in 1902, is a diversified energy company with a long-standing history and presence in New York and Pennsylvania. National Fuel Gas Supply Corporation is part of National Fuel Gas Company’s Pipeline & Storage Segment, owning and operating nearly 2,800 miles of interstate natural gas pipelines.

collaboration icon

Contact Information

Amanda Nelson
Communications Coordinator
Corporate Communications
814-871-8148

NY Home NY Business
PA Home PA Business